 | Our engineering team handles the technical aspects of the building and ensures that the design is optimized to meet all aspects of its vocation. |  | While the foundations are being installed at the job site, the Murox® building system components are being fabricated under ideal conditions back at the plant. Special care is given to the installation of the insulating materials. |  | The windows and pedestrian doors are also factory installed. |  |
 |
|  |  |  |  |  |
 | Day 1
 |  | Day 2
 |  | Day 3
 |  |
 | Murox building system components are delivered to the site. |  | Installation of the structure and panels begin simultaneously. |  | Assembly of walls and structure continues. |  |
 |
|  |  |  |  |  |
 | Day 4
 |  | Day 5
 |  | Day 8
 |  |
 | Installation of the steel deck begins. |  | Erection of structural steel and walls is completed. The installation of steel deck is also finished and plumbing work can begin. |  | The building shell is now complete. Other sub-trades can take over the job site while Murox® completes the finishing work. |  |
 |
|  |  |  |  |  |